Town of Wickenburg | Wickenburg, Arizona
This project includes the replacing of existing 4-inch lines with 8-inch lines. Existing fire hydrants were also replaced within the project area, and an 8-inch line was installed on Swilling Avenue between the existing 8-inch CIP water line and 12-inch ACP waterline. The project also included 39 service reconnections. These connections were designed and constructed in such a way as to minimize the period of time any customer was out of water. In addition to pre-design and design services, EPS Group also completed bid services and post-design services. We assisted the Town of Wickenburg with the bidding of the projects, reviewed bids, and made a recommendation of the award. Post-design services included construction administration and processing the project through the Maricopa County Environmental Services Department for the Approval of Construction on this CDBG-funded project.